Control Tower & New Doha Port Project (NDPP) - NP0064

Client: New Doha Port Steering Committee

Duration: 1 year

Requirements: Dewatering for a 40 x 50x -7m (Length x width x depth) excavation to the sea.


Project Details:

Dewatering was done adjacent to the sea in New Doha Port Project, the project have an excavation of 40 x 50 m (length x width). UH challenged all expectations by implementing a dewatering system including 13 heavy duty pumps with standby units, UH succeeded in granting a dry and safe area as desired by our client with a pumping capacity of 800 m3/hr. UH received an appreciation certificate from CDC for the challenging dewatering work that we´ve done in this remarkable job.