Al Wakrah Stadium-Enabling Package

Client: Qrail

Scope: Water treatment and monitoring system

Duration: 3 Months

Requirements: Water treatment of 25,00 m3/day of contaminated water generated from the ground water Control System.


Project Details:

UH has been hired to treat the pumped ground water which has been contaminated by high percentage of coliforms including E-coli. Our system within 2 days managed to control the contamination in the pumped water in addition to controlling the e-coli in the existing lagoon, so that water quality met with the MME specification.